Note: must register at site to access full RFP (registration is free).
Pre-tender meeting 03/10/2010.
General description:
The construction of a pipeline which will tie in to a new pipeline. This contract will include:
1. Directional Drilling of approximately 10,000 m of 150 mm diameter HDPE DR 11 c/w approved trace wire supply and install.
2. Crossings:
Secondary Road 824
800 m private land
Various utilities as provided in Appendix A
3. Valves, fitting and related appurtenances.
4. Provisional Work:
Directional Drilling of approximately 2,000 m of 150 mm diameter meter HDPE DR 11 c/w approved trace wire supply and install
Valve fitting and related appurtenances