The Project consists of the following major items:
- Schedule A
 120± linear feet of 8-inch gravity sewer point repairs
ï‚· (6) 4-foot diameter manhole replacements
ï‚· 159 Manhole frame and cover replacements and repairs
 213± Vertical feet of manhole rehabilitation
ï‚· Miscellaneous Manhole repairs
ï‚· Miscellaneous sanitary sewer lateral repairs, replacements and abandonments
ï‚· Miscellaneous Pump Station Repairs and Improvements
ï‚· Supplementary work items
- Schedule B
 785± linear feet of new 8-inch gravity sanitary sewer lines and Pump Station abandonment