The work generally consists of the following items:
1. Reshape existing berms 14,105 m2
2. Supply and install geotextile (amoco200) 10,110 m2
3. Supply and place erosion protection gravel 1535 m3
4. Replace damaged control structures 11 each
5. Dredging of existing lagoons 19,200 m2
6. Drying, storing of lagoon sludge 19,200 m2
7. Pumping of lagoon cells L.S.
8. Remove and replace existing fencing c/w paige wire fencing 3,420 m