The Work under this Project consists of furnishing all, labor, materials, equipment, supplies, permits and fees for the construction of sanitary sewer improvements and water distribution system improvements including, but not limited to approximately:
535 LF of 8 PVC (SDR 26) Sanitary Sewer Main
2,164 LF of 8 PVC C-900 Sanitary Sewer Main
887 LF of 8 D.I. Sanitary Sewer Main
281 LF of 18 PVC C-905 Sanitary Sewer Main
3,496 LF of 8 PVC Water Main
267 LF of 12 PVC Water Main
19 Sanitary Sewer Manholes
All incidental work thereto as detailed in the Contract Documents.