Mandatory pre-bid meeting 05/04/2010.
SCOPE OF WORK:
Per plans and specifications to furnish, fabricate, deliver and install all work associated with the
Structural Steel and Security Mesh Systems above the exercise yards. Including but not limited to
shop drawings for architectural review and approval, plates, attachment anchors, primer, finish,
angles clips, anchors screws, grout sealant, caulking, fasteners and any other miscellaneous metals
and/or any other related items and incidentals necessary to provide complete Structural Steel and
Security Mesh System.
and
Per plans and specifications furnish, fabricate, deliver and install all work associated with but not
limited to the prefabricated metal stairways, and mezzanine guard rails. Shop drawings for
architectural review and approval, iron and steel pipes, plates, bars, tubes, attachment anchors,
primer, finish, angles clips anchors screws, continuous steel angles, grout sealant caulking, fasteners
and any other miscellaneous metals and/or any other related items and incidentals necessary to
provide complete metal stair and railing systems. Coordinate with Precast concrete vendor,
electrical, plumbing, roofing and fire protection contractors to ensure that the installation of the steel
shall not interfere with any other work being performed and also to communicate with said
contractors regarding the synchronization of the scopes.