Scope of Work: After replacement of existing service- conducted by Channel Island Beach Communities Services District, we wil begin the process of raising the existing 4" meter above ground. Remove existing meter and piping. Demo vault where conflicts with concrete pad for meter assembly. Place 4" riser to set 4" meter assembly. Backfill existing excavation/vault and prep for concrete. Set meter assembly and pour concrete pad. Clean up work area and certify backflow.
ROBERT R. JACKSON, STOREKEEPER FIRST CLASS , Phone 3105213645, Fax 3105213654, Email ROBERT.R.JACKSON@USCG.MIL