Non-mandatory pre-bid conference 08/03/2010 (attendance strongly encouraged).
Base Bid:
Taxiway ‘B’ Relocation (‘B4’ �" ‘B6’):
This Work consists of realigning approximately 1,200 linear feet of Taxiway ‘B’ between
Taxiways ‘B4’ and ‘B6’ and includes approximately 2,000 tons of asphalt paving, 2,600 cubic
yards of crushed aggregate base, 5,000 cubic yards of excavation, 1,400 square feet of
pavement markings, 7,000 linear feet of taxiway cabling and edge lighting, as well as taxiway
signage, and various erosion control items.
South Parallel Taxiway Realignment:
This Work consists of realigning approximately 1,200 linear feet of Taxiway ‘B’ between
Taxiways ‘B1’ and ‘B2’ and includes approximately 1,500 tons of asphalt paving, 1,900 cubic
yards of crushed aggregate base, 300 linear feet of storm drainage, 3,000 square feet of
pavement markings, 3,500 linear feet of taxiway cabling and edge lighting, as well as taxiway
signage, and various erosion control items.
South Apron Expansion:
This Work consists of expanding and rehabilitating the South Apron and includes
approximately 3,000 cubic yards of excavation, 14,000 square yards of pavement milling,
cracksealing, 9,000 tons of asphalt paving, 1,000 linear feet of storm drainage, 4,000 square
feet of pavement marking and various erosion control items.
Additive Bid:
South Parallel Taxiway Hold Apron:
This Work consists of preparing, paving, marking, and lighting the South Holding Apron and
includes approximately 5,000 square yards of lime-treated subgrade, 1,400 cubic yards of
crushed aggregate base, 1,200 tons of asphalt paving, 1,000 linear feet of taxiway cabling and
edge lighting, as well as grassing and various erosion control measures.