THIS MODIFICATION IS HEREBY ISSUED TO ADD CONTRACTOR PRODUCTION LOT TESTING REQUIREMENTS TO CLIN 0004 (NSN 2915-01-566-6707). CONTRACTOR FIRST ARTICLE TESTING STILL APPLIES TO THIS CLIN. THE SAMPLE SIZE FOR THE FIRST ARTICLE TEST IS 2 EACH. THE REQUIRED DELIVERY TIME FOR THE FIRST ARTICLE TEST REPORT IS 210 DAYS ARO. THE GOVERNMENT REVIEW TIME FOR THE FIRST ARTICLE TEST REPORT IS 180 DAYS. THE SAMPLE SIZE FOR THE CONTRACTOR PRODUCTION LOT TEST IS 1 EACH. THE REQUIRED DELIVERY TIME FOR THE CONTRACTOR PRODUCTION LOT TEST REPORT IS 210 DAYS AFTER FIRST ARTICLE APPROVAL. THE GOVERNMENT REVIEW TIME FOR THE PRODUCTION LOT TEST REPORT IS 60 DAYS. THE REQUIRED DELIVERY TIME FOR THE PRODUCTION UNITS IS 30 DAYS AFTER PRODUCTION LOT TEST APPROVAL. THE TOTAL DELIVERY TIME IS 690 DAYS ARO. THE SOLICITATION CLOSING DATE HAS BEEN EXTENDED TO FEBRUARY 21, 2019.