The work, in general, consists of cold planing 10' sections at beginning and end of project; pulverizing in place entire width of project limits; removing approximately 0.25' of pulverized material; stockpiling pulverized material; excavating earth; constructing concrete cutoff and end walls; compacting remaining pulverized material in place; placing 0.10’ Type A, ½” Max., PG 70-10 asphalt concrete over compacted pulverized material; placing 0.15’ Type G, ½” Max., PG 64-16 rubberized asphalt concrete over paved surface; painting traffic stripes and pavement markings; hauling removed material to nearby road and spreading and doing other work appurtenant thereto.