Non-mandatory pre-bid meeting 05/28/2010.
SCOPE OF WORK
This work consists of furnishing all labor, equipment, tools and materials; and performing
all operations in connection with the construction and installation of the specified work, complete
and in strict accord with these specifications and/or plans. Fencing is required to be installed as
shown on the contract drawing or as directed in the field.
The Contractor shall supply and install a six-foot high outfield fence on the existing large
baseball field. Layout and dimensions are shown on project drawing. Outfield
fence shall include top and bottom rails. Four-foot high sideline fences as shown on drawing are
to be installed to connect from existing sideline fences to the outfield fence as shown on
drawing.