The City is seeking proposals from qualified vendors for renovations to an interview room.
Phase I
ï‚·
Venting and other miscellaneous openings to be covered for dust control.
ï‚·
Cut access holes in concrete block walls for six (6) new doorways.
ï‚·
Install lentils at all new doorways
ï‚·
Install new door jambs and re-use owner’s doors and hardware
ï‚·
Block in double door in hallway and one (1) door to existing office from other hallway and patch where necessary.
Phase II
ï‚·
Venting and other miscellaneous openings to be covered for dust control
ï‚·
Build new three (3) 8’x8’ concrete block walls and one (1) 8’x12’ concrete block wall for office partitions
ï‚·
Install one (1) new door jamb and re-use owner’s doors and hardware
ï‚·
Paint new walls and jamb
ï‚·
Patch in vct tile where necessary