A MANDATORY SITE VISIT IS REQUIRED FOR
VENDORS TO FULLY UNDERSTAND WHAT IS
INVOLVED AND REQUIRED TO COMPLETE THIS
JOB SUCCESSFULLY. FAILURE TO MAKE
THE MANDATORY SITE WILL RESULT IN THE
REJECTION OF YOUR BID.
B. VENDOR TO INSTALL ALL NEW ROOF:
B1. REMOVE EXISTING ROOFING, VENDOR MUST
COMPLETELY REMOVE EXISTING ROOF DOWN
TO THE DECKING.
B2. VENDOR MUST REPLACE ALL ROTTEN WOOD,
INCLUDING DECKING AND CORNICES.
B3. VENDOR MUST RAISE ALL SUNKEN AND LOW
SPOTS IN ROOF TO ORIGINAL PITCH.
B4. INSTALL NEW 15 LB. ROOFING FELT.
VENDOR MUST LIST THE LB ROOFING FELT
THEY ARE BIDDING IN THE SPACE
PROVIDED BELOW TO ENSURE THAT ALL
VENDORS UNDERSTAND WHAT LB ROOFING
FELT MUST BE PROVIDED.
ROOFING FELT __________ LB.
B5. INSTALL THREE DIMENSIONAL SHINGLES,
35 YR. WARRANTY. ALL VENDORS MUST
LIST THE YR WARRANTY OF THE SHINGLES
THEY ARE BIDDING IN THE SPACE
PROVIDED BELOW TO ENSURE THAT ALL
VENDORS UNDERSTAND WHAT YR WARRANTY
SHINGLES MUST BE PROVIDED.
SHINGLE WARRANTY _________ YRS.
B6. COLOR OF NEW SHINGLES TO APPROXIMATE
COLOR OF EXISTING SHINGLES.
B7. VENDOR MUST INSTALL NEW BOOTS ON ALL
PLUMBING AND EXHAUST VENTS, AND
ELECTRICAL POWER DROPS.
B8. VENDOR MUST INSTALL ALL NEW DRIP
METAL.
B9. ALL ROOFING NAILS MUST BE 7/8"
GALVANIZED OR GREATER.
C. VENDOR TO SUPPLY ALL MATERIAL, LABOR,
LABOR, AND INSURANCE.
D. VENDOR TO PROVIDE CLEANUP AND REMOVE ALL DEBRIS AFTER WORK IS COMPLETED.