Non-mandatory pre-bid meeting 03/09/2010.
Work consists of all labor, tools, materials and equipment necessary to replace catch basins,
replace catch basin tops, connect existing drainage pipe to new structures, installation of granite
curbing, installation of bituminous concrete curbing, reset manhole tops, remove and replace
concrete driveway aprons, construct bituminous driveway aprons, installation of bituminous
concrete for patching may be required, mill 38,000 square yards of roadway and pave
approximately 6,000 tons of bituminous concrete, storm drainage improvements, excavation, saw
cutting of concrete, saw cutting of bituminous concrete pavement and as well as miscellaneous
work.