This is a subcontracting opportunity with Red Rock Job Corps Center/Adams & Associates Inc. and not with the U.S. Department of Labor
Scope of Work
Contractor shall clean, abrasive blast, then use 4 step coating system to refinish one of the existing Potable water tank. Contractor shall verify the exact square footage of paint to be applied. Center has estimated that the tank approximately 2,900 sq. Ft.
* The complete bid package is attached.
* All interested parties must attend the pre-bid walk through scheduled for May 14, 2014 at 3:00pm EST..
* The contractor must include with his/her proposal, certification that he/she will conform to the latest Davis Bacon Wage Rate decisions for the area. See section VII for wage determination.
Theresa Insinger, Purchasing Agent, Phone 5704770203, Fax 5704775280, Email [email protected] - Robin Young, Purchasing Assistant, Phone 570-477-0192, Fax 570-477-5280, Email [email protected]