1. Demolition of the top of a concrete curb (approximately 8” deep, 2’ wide and 116’ long) down to finish floor grade.
2. Fill in an adjacent ramp to finish floor grade ( approximately 14’ wide and 130’ long
3. Construction of a new pushwall adjacent to the ramp (approximately 8” wide, 11’ high and 116’ long).
4. Construct a new personnel exit door for the Organics Area on the west wall of the building.
5. Extend an existing 12” wide, 12’ high pushwall, approximately 14’ to close off an existing rollup door opening.
6. Demolition of an existing pushwall adjacent to the ramp (approximately 12” wide, 7’ high and 130’ long). It appears that this task will be the most disruptive to ongoing Organics Area operations and should be done last.