Miller Parkway Water Main Extension
Project #WA0622
The project will include but not limited to the following major categories of work:
Excavation 226,400 CY
Embankment 86,300 CY
8" DIP Water Pipe 381 LF
12" DIP Water Pipe 4,711 LF
Bore and Encase 12" DIP Water Pipe 85 LF
Pressure Reducing Valve Setting 1 LS
Project must be complete in 270 calendar days. Grading of the western most 1,000 feet of roadbed must be complete in the first 120 days of the contract