The previously posted items and quantities required for First Article Testing are obselete and replaced with the following:
Item
Quantity
Complete Medium Helmet System
57
Complete X-Large Helmet System
56
Unfinished Med. Shell
4
Unfinished X-Large Shell
4
Finished Med. Shell
7
Finished X-Large Shell
6
Pad Set
26
Hook Disks
40
Inner Layer Pad Material
7
Outer Layer Pad Material
1
Retention System Webbing
5
Complete Retention System
7
The Items and Quantities for the base and all options remain unchanged.