This is a combined synopsis/solicitation for commercial items prepared in accordance with the format in Subpart 12.6, as supplemented with additional information included in this notice. This announcement constitutes the only solicitation; proposals are being requested and a written solicitation will not be issued.
Maneuver Systems Sustainment Center Bridge Crane System, (FY14 MSSC Phase III), requires the purchase, installation, commissioning, warranties and training of a combination of upper cranes and lower cranes totaling 119 bridge cranes in Building 412. The heavy upper cranes will be top running bridge, with under hung hoists, in 20-Ton capacity. The lighter lower cranes will be under hung bridge, with under hung hoists, in dual 3-Ton hoists capacity (two hoists on a single bridge capable of tandem lift for a total of 6-Tons).
Sara Jackets, 409-766-3846
USACE District, Fort Worth