The scope of work for this project consists of:
1. Demolition of an existing sewage lift station and miscellaneous underground utilities.
2. Construction of a new lift station consisting of a 5 ft dia x 9 ft deep precast concrete wetwell supported by a 8 ft dia x 1.5 ft thick reinforced concrete slab and capped with a precast top cover; Two (2) submersible pumps (3 hp each); a 4 ft x 4 ft x 3 ft precast concrete valve box; In place, complete, including all required piping, appurtenances and site restoration.