Estimated Construction Cost: $3,000,000
This project replaces a twenty-one year old SimplexGrinnell 2120 fire
alarm system at the Convention Center. Portions of the
original system have been upgraded to 4100 SimplexGrinnell
System. This project shall provide for a state of the art system with
appropriate monitoring, management and integration. It will include
replacement of existing fire alarm system devices, new fire alarm
panels and system components, programming, testing and
coordination as required throughout the facility. The contractor will
be required to utilize existing conduit and wiring where possible and
install new raceways and wiring where required. All wiring shall meet
system manufacturer's requirements. It is anticipated that new Fire
Alarm System will be installed side by side along the existing system
by utilizing components furnished by Simplex, Siemens, Edwards or
other approved equal manufacturer. It is anticipated that a phased
cut over of the new system will be required. Throughout the duration
of the construction process the contractor shall maintain complete
coverage and operation of the fire alarm system.
Additional: http://www.mccahome.com/download/Current_Bid_Opp/2010/FAAttachmentA.doc