The work will consist of road reclamation, stabilization, paving and graveling. 4 Roads are involved. The Town will be replacing all culverts prior to the work
commencing. The Town will also be purchasing and placing stabilization
fabric, bank run gravel and crush gravel on Sugarbush Road after the pulverization and compaction. The Town will provide traffic control as needed for the project.