GRAND MERE VANESTA
UNIT THREE
2009 IMPROVEMENTS
SANITARY SEWER PROJECT NO. SS0905
WATER MAIN PROJECT NO. WA0902
STREET PROJECT NO. ST0904
No. Quantity Unit
ITEM DESCRIPTION
1 8 Sanitary Sewer Pipe 1,575 LF
2 4 Sanitary Sewer Pipe 934 LF
3 Standard Manhole 8 EA
4 8 D.I.P. Water Pipe 200 LF
5 6 D.I.P. Water Pipe 206 LF
6 Fire Hydrant Setting 1 EA
7 8 1/2 Asphalt Pavement
(Part C1) 5,760 SY
8 6 Reinf. Conc. Pavement 6,750 SY
9 Earthwork 22,200 CY
10 Storm Pipe 340 LF
11 Concrete Curb & Gutter 3,810 LF
TIME LIMIT: 135 Working Days