Construct a high-bay, Weapons System Trainer (WST), addition to existing flight simulator facility 1231, at Little Rock AFB, Jacksonville, Arkansas. The addition is to mirror the existing facility architecture and include concrete footings and slab on grade, structural steel frame, standing seam metal roof, brick exterior walls, fire protection/ suppression. Support areas include classrooms, briefing rooms, secure rooms, offices, restrooms, storage, communications equipment room, electrical/hydraulic/mechanical room, and circulation. Site work includes special foundations, asphalt access roadway, and concrete walkways. Applicable force protection measures to be incorporated IAW DoD and USAF Installation Force Protection standards and Leadership in Energy and Environmental Design (LEED) standards.
Magnitude of Construction $1,000,000.00-$5,000,000.00.
Glenn Jenkinson, 501-324-5720
USACE District, Little Rock