Adding two 9’X9’ box culverts to supplement the flow capacity of two existing 10’X9’ box culverts, raising approximately 400 linear feet existing roadway profile a maximum of 1.45’, replacing existing sidewalks, replacing existing bridge rail with metal beam guard rail, adjusting existing utility structures to proposed grade, installing a storm drain network with 3 curb inlets, channel grading and excavation, installation of rock gabion wall.