The intent of this project is to extend the service life of existing pavements in several campgrounds in the Bridgeport and Carson Ranger Districts on the Humboldt-Toiyabe National Forest through crack sealing and incidental striping. The project includes work at several locations in two general areas:
T4N, R24E, MDB&E, Approximately 15 miles southwest of Bridgeport, CA off of Buckeye Robinson Creek Road: (BASE ITEMS)
PAHA CAMPGROUND: Perform crack sealing according to the schedule of items.
CRAGS CAMPGROUND: Perform crack sealing and pavement repair according to the schedule of items.
LOWER TWIN LAKES CAMPGROUND: Perform crack sealing according to the schedule of items.
ROBINSON CREEK CAMPGROUND: Perform crack sealing according to the schedule of items.
Approximately 60 miles south of Carson City, NV on Hwy 395: (OPTIONS 1, 2 & 3)
BOOTLEG CAMPGROUND: Perform crack sealing according to the schedule of items.
CHRIS FLAT CAMPGROUND: Perform crack sealing according to the schedule of items.
SHINGLE MILL DAY USE AREA: Perform crack sealing according to the schedule of items.
ALL LOCATIONS:
Work shall be performed in accordance with the STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS, (FP-03), and the Forest Service Supplemental Specifications (FSSS).
Tanya Spanfellner, Contracting Officer, Phone 208-373-4130, Fax 208-373-4197, Email [email protected]