This project will be advertised as a Total Small Business Set-Aside.  Only small businesses will be allowed to bid as a prime contractor.

The Arroyo Seco Road project is located in the County of Monterey on California Forest Highway (FH) 129, otherwise known as Arroyo Seco Road, near Greenfield, CA in the Los Padres National Forest.  The proposed project is for restoration, resurfacing, and rehabilitation of 4.7 miles of roadway between the Arroyo Seco Campground and the intersection with County Road G16 (Carmel Valley Road).    Heavy seasonal traffic controls commencement and termination of construction operations.  There will be uninterrupted traffic until after Labor Day up through the following Memorial Day weekend. Temperature dependent work items such as asphalt paving and pavement marking must be completed in dry conditions, for which the duration is also limited. 
The major work elements include pulverizing the existing road to a depth of 4" and a 3" asphalt surfacing.   The primary scopes of work are slope stabilization, subexcavation, pulverization, aggregate base, asphalt pavement, drainage improvements, signing, and pavement markings.  Significant quantities include:

Line Item                   Unit                  Est. Quantity                           

Subexcavation            CUYD            2,600                                  

Pulverizing, 4-inch depth    STA                      253                                

Roadway Aggregate           TON                      2,200                             

Hot Asphalt Conc. Pavem't TON                      11,700                                          

Prime Coat                              SQYD                    71,000                                 

Standard Underdrain          LNFT                     920                                

Concrete Curb, 18" Depth   LNFT                       4730                                   

It is anticipated that this project will be advertised in mid to late July with construction occurring from late August, 2014 into early summer 2015, with winter shut-down likely.

The contracting range for this project is between $3 million and $4 million.


Jeremiah Rogers, Phone 7209633090, Email [email protected] - Jason Longshore, Phone 7209633090, Email [email protected]