The project is to replace current ice cooling system and its subsequent conversion to chilled water system. In
addition to the above the associated rooftop cooling tower will need to be reconditioned.
The goal is to create two isolated chilled water loops, one for level 15 (computer operations) and partial level
16 (ups power room), and the second loop for the building loads all within the allocated funding.