Complete Contract Documents July 31, 2009
Complete FAA Review August 7, 2009
Advertise for Bids (Wednesday) August 12, 2009
Advertise for Bids (Sunday) August 16, 2009
Contract Documents available August 17, 2009
Pre-bid Conference (Mandatory) September 2, 2009
Bid Opening September 16, 2009
City Council Working Meeting September 24, 2009
City Council Regular Meeting October 1, 2009
Notice of Award October 5, 2009
Execution of Contract October 14, 2009
Preconstruction Conference October 14, 2009
Issue Notice To Proceed October 15, 2009
Start Construction (NTP Phase 1) October 19, 2009
Complete Construction
(270 cd from NTP Phase 1) July 15, 2010