I. GENERAL SCOPE OF WORK
The Architect / Engineering firm shall plan and design upgrades to comply with USP 800 and USP 797 at the Murfreesboro Campus, renovating approximately 2500 square feet. The design consultant shall provide all necessary architectural and engineering (A/E) services to completely evaluate the pharmacy Compounding Sterile Preparations (CSP) operations, processes and infrastructure in existing and adjacent affected spaces in order to develop concepts and provide a complete design. The A/E shall provide space planning, testing, technical reports, layouts, calculations, sizing, narratives, estimates, schedules and phasing plans to present concepts and fully discuss options. After the optimal solution is selected, the A/E shall develop a complete design and produce construction bid documents. Professional disciplines include, but are not limited to, USP design specialist(s), architectural, life safety, mechanical, plumbing, electrical, communications, security, access controls, industrial hygiene and commissioning.


II. STATEMENT OF PROJECT OBJECTIVES AND CONCEPT
It is the intent of the VA TVHS to be USP 800 compliant by December 2019, while also increasing the quality of USP 797 facilities and operations. In the current facility planning concept for the project, the pharmacy and the building footprint will expand, enabling USP improvements while the existing compounding rooms remain operational during the new construction. The new USP 800 and USP 797 space will be added onto the building, connecting to the adjacent pharmacy. The existing USP 797 space will remain operational until the new USP 800 and USP 797 space is commissioned and in service, then the existing USP 797 containment rooms will be converted for pharmacy operations. The A/E will fully investigate, survey, test, analyze, interview key personnel, document existing conditions, infrastructure, systems, equipment and processes, to gain the knowledge and insight necessary to prepare a quality design to meet the following objectives:
Upgrade USP 797 operations and containment rooms

Provide USP 800 compliant containment rooms and operations

Increase capacity, productivity and functionality of the Pharmacy

Improve flow and alleviate congestion

Improve processes and staff efficiency

Reduce downtime and improve reliability

Promote uniformity between the TVHS campus pharmacy operations at the Nashville and Murfreesboro Campuses

Ensure that USP operations can evolve and grow. Currently, the facility has two hoods (1 positive and 1 negative). However, the current design and construction shall accommodate the future projected program growth to 2 IV prep hoods and 1 chemo hoods with minimal alterations.

Plan and design secondary CSP provisions to be used during planned and unplanned outages.

Commission the project by implementing a process throughout design, construction, inspecting and testing. The focus shall be on providing a complete, working product that complies with all codes/standards/guidelines.



III. STATEMENT OF A/E TASKS
Perform a complete assessment (functional, infrastructure, operational, etc.) at both facilities developing a minimum of three, unique concepts to comply with both USP 800 and USP 797. Each concept shall be a specific solution that is independent and unique. A variance or modification of a concept theme is not unique and shall not be considered as another concept or alternative solution. Substituting a constructed, built solution in lieu of a modular solution shall not be considered as another unique concept or solution (and vice versa).
Evaluate all components, materials, supplies and equipment associated with the CSP. Present alternative options and propose best practices.
Design shall also weigh the benefits and risks of modular systems (manufactured offsite and assembled onsite) verses solutions that are totally built at the site. On-site interviews and discussions shall occur during schematic development and a narrative included in the schematic submission. This topic shall be fully discussed during the schematic submission review meeting and resolved prior to DD1. Pricing and lead times shall be broken down with submission for each choice (modular and stick built).
Provide dimensioned layouts of the space with flow diagrams, furniture placement, and equipment selection, incorporate utility tie-in locations, and address any impact moves or construction during the schematic phase. This should be done to prove the validity of concepts, as well as the final solution(s).

Provided complete concepts and designs that include impact moves, phasing, and staging plans for upgrading the USP 797 pharmacy facilities, while adding USP 800 compliance. Planning and design shall include any medical center spaces and operations impacted by the pharmacy upgrade. The TVHS Space Planner will not develop the plans or provide space planning, but will work with the consultant to determine the availability of space and evaluation the overall effects to services / spaces / functions. A/E s space planner shall interface with the VA space planner as part of schematic development and follow-up during DD s to ensure proper space allocation and planning. These meetings will be separate from scheduled submission reviews.
Once the design team comes to a consensus, selecting the best concept, the A/E shall fully develop the selected concept and provide complete construction bid documents.
The A/E shall furnish all services for planning and a complete Schematic Design (SD) through Construction Documents 2 (CD2), and then produce construction bid documents.
1. Necessary site survey work and evaluation during the SD phase, such as verifying existing conditions, observing and verifying operational processes, verifying record drawings, and verifying and analyzing utility systems shall be accomplished for the preparation of accurate Design Development submissions. A/E shall furnish documentation and drawings of these findings, and address deficiencies in the design process.
2. The complete site survey work shall include a thorough investigation of existing conditions to accurately document and convey space dimensions for measured drawings, all utilities for affected areas, and utilities that traverse through affected areas, typical construction type and variations, and finishes. This information provides the necessary base drawings for the Schematic Development phase and Design Development.
3. Utility system verification shall include, but not be limited to, the necessary testing, adjusting, and/or balancing (TAB), temperature testing/surveillance, visual inspection, Direct Digital Controls frontend trending and other innovative measuring and testing methods of affected systems to ascertain the existing operating and performance conditions that will impact the design and construction process. Systems that are insufficient in capacity or are no longer supported by OEM parts shall be considered for expansion and/or replacement. Document existing conditions, proposed alternatives, and corrective actions.
Design shall meet VA needs, VA space criteria, VA design alerts, and VA design guidelines / standards and other applicable regulations (USP, CETA, etc.).


The A/E shall incorporate Energy efficiency and cost savings shall be considered in all design decisions. Design to applicable sections of the TVHS Energy Requirements and Design Guide for specific energy guidance. Design shall incorporate, but not be limited to:
All components of the supply, ventilation, and exhaust systems will be evaluated and upgraded to meet hospital standards, increase functionality, energy efficiency and building envelope maintenance. Include Direct Digital Controls (DDC) and optimization controls. Whenever possible, exhaust systems shall be converted to return.

Optimize reliability, stability, monitoring, and control. Integrate native BACnet DDC controls with existing DDC frontend systems. Provide strict control of processing environment (temperature, pressure relationships, and humidity, etc.).

When observed, include design for replacement or repair of duct work/duct access doors/access panels that are leaking air. Duct work leakage objective is to obtain ASHRAE Standard 90.1, Seal Class A on major supply lines and Seal Class B on return and exhaust lines.

The A/E shall form a design team consisting of key designers and key VA personnel, including affected users and services, and conduct meetings to accomplish a cohesive design that addresses facility issues and concerns. Design team meetings shall be held on site in conjunction with each phase of design and each submission. Additional meetings with individual user groups will be necessary to gather information and produce an effective design.

The A/E shall provide 3design concepts as part of the Schematic Design phase. The A/E shall provide narratives and present the concepts to the VA Design Team and fully discuss the merits (pros and cons) of each. The A/E shall, document team/staff feedback and facilitating discussions used to arrive at a consensus. The design team will select the concept that the A/E will be fully developing during Design Development and Construction Documents.

The required stamp of the licensed architect and/or engineer of record will be considered as certification of compliance with the contract requirements for that document. The registered individuals who will stamp the final construction bid documents shall be the same lead designers that accomplish the assessments, surveys, interviews and design work.
Design shall ensure proper life safety, including egress, proper fire/smoke compartmentation, fire alarm, sprinkler system, etc. The A/E shall provide a separate stamped Life Safety Sheet for the areas in question within the submitted drawings. In accordance with VHA Directive 7712 the final Fire Protection code review will be vetted by a VA provided 3rd party. Any comments by the 3rd party will be addressed and revisions made accordingly by the A/E. A/E shall submit a stamped Life Safety sheet(s) as part of the CD1 package and final construction bid documents.
The AE shall provide commissioning agent(s) to perform complete project commissioning throughout the design and construction, covering all trades/disciplines and all codes/standards/guidelines. Commissioning will also be an integral part of the QA process. VA is assigning the 3rd party commissioning responsibilities to the A/E s commissioning agent(s) to provide unbiased oversight. Commissioning tracking sheet shall relate design issues and responsible party with decisions, code compliance and resolutions. The Commissioning Agent shall maintain a tracking sheet, mapping all code compliance issues from inception, review and resolutions. Commissioning tracking sheet line item activities shall include, date, issue, review and decision, responsible A/E designer and satisfactory resolution. The Commissioning Agent s updated comments will be included with each submission. Since the A/E is solely responsible for the design, VA Directed shall not be an acceptable explanation of compliance or resolution. The commissioning agent shall simultaneously copy the VA COR and Contracting Officer when producing/conveying any commissioning work product, (correspondence, reports, observation lists, tracking, etc). The commissioning agent shall submit a stamped final commissioning report to the VA COR, Contracting Officer, contractor and vendor. Any issues shall be discussed in group meetings and resolved to the satisfaction of the commissioning agent, then incorporated into the final revised, stamped commissioning report. A/E shall provide stamped as-built drawings.


A/E shall develop and execute a Quality Assurance (QA) plan that demonstrates a team approach and methodology throughout all aspects of the entire design. Commissioning shall be integral to the QA process. The QA process shall drive design review, improvement and code compliance, including fully documented comments / issues and resolutions / corrections. The QA plan shall be submitted to the VA along with the design schedule and shall describe the QA tasks that will be performed through various phases of the design, including review of submissions. The design QA effort shall be led by the commissioning agent and a senior design engineer. In addition to the design engineers performing project design work, the QA team shall include another USP 797 and USP 800 specialist(s) (that meets the qualifications for the primary USP 797 and USP 800 specialist(s)) and another senior engineer that is not performing actual design work on this project. VA COR shall be invited to all QA and commissioning meetings. Completion of each QA task shall be initialed and dated by the responsible QA team member. A 100% completed QA review shall be submitted with each A/E design submission, including the final construction bid document submission package. Cost review and control shall be part of each phase of the QA process and each design submission. The QA process shall produce deliverables included with each submission package; including redline mark-ups and commissioning tracking sheets. QA teams shall review issues with the design team so corrections can be made prior to submission of each package. Commissioning Agent shall be involved throughout design, construction, installation, inspection, trending, testing and certification. At the completion of the project, the Commissioning agent shall provide a stamped report indicating compliance with all applicable codes/standard/guidelines (refer to Construction Period Service Requirements below).

A/E will coordinate with leading industry equipment manufacturers and vendors to ensure proper layout and support of equipment according to manufacturer s requirements. A/E shall interface with various equipment providers, including modular solutions, to find the best working solution for TVHS, including all components, options, arrangements, utilities, etc. All selections shall promote fair and open competition.

Preliminary facility planning has yielded a construction budget with a magnitude of approximately $1,700,000 to $2,300,000. A/E shall provide an independent estimate, arriving at a specific, construction total for a complete, working project, including all equipment, phasing and temporary measures.
Planning and design shall account future program growth with minimal alterations or upgrades. Design shall incorporate an appropriate safety factor. For systems, an appropriate safety factor would be 15%. Safety factor shall also be applied to future growth of 33%. Current design in Murfreesboro is 2 hoods (1 positive and 1 negative). Future design projections for Murfreesboro CSP are to add one (1) more hood for a total of three (3; two positive and 1 negative).

Design to minimize disruptions to medical center and pharmacy operations during construction and after project completion. Design shall allow for easy access, replacement and modification of components, minimizing rework, repair, patch-back and upgrade durations.

Individual room or component failures must be corrected and returned to services within 24 hours.

Design shall limit system failures affecting multiple rooms. In the case of a multiple room outage/failure, corrections shall be made and a hazardous room and a non-hazardous room must be returned to services within 24 hours.

Components and equipment shall be easily replaceable / swappable. Outages resulting from component failures shall be corrected and affected rooms returned to service within 24 hours.

Work to perform moderate upgrades/improvements to the containment rooms, such as the addition of a containment hood or replacement of multiple doors and automatic operator assemblies, shall be possible within a 3-day weekend (Thursday night through Sunday, including testing).




Other project constraints and considerations are as follows:
Construction will add new building square footage at the Murfreesboro Campus, expanding the building footprint.
Since immediate supervision of the CSP is required, solutions that do not create staffing inefficiencies are preferred. Solutions that minimize travel distances are preferred.
The controlled area outside the containment rooms shall affectively limit traffic and cross contamination.
Utilities shall not be surface mounted or exposed, especially on the exterior of the building.

IV. BASIS FOR DESIGN
Comply with Department of Veterans Affairs standards/guidelines, which may be obtained from the internet (http://www.cfm.va.gov/TIL/), including (but not limited to) the following:
Department of Veterans Affairs Design Manuals. http://www.cfm.va.gov/til/dManual.asp
Physical Security Design Manuals for VA Facilities. The facility shall be considered Mission Critical. http://www.cfm.va.gov/TIL/spclRqmts.asp.

VA HVAC Design Guidelines at http://www.cfm.va.gov/til/dManual.asp. Indoor air quality requirements must be met / maintained, such as outside air percentages, air changes / CFM, and humidity. Design shall maintain building envelopes to prevent moisture infiltration and possible mold growth.

VA TIL, PG-18-3, Design and Construction Procedures http://www.cfm.va.gov/TIL/cPro.asp
Topic 1 - Codes, Standards and Executive Orders
Topic 2 - Drawings
Topic 15 -B Energy efficient and sustainable design policy for new construction
Topic 16 - Sustainable buildings policy for new and Renovation construction

VA TIL, PG-18-15, A/E Design Submissions and Review. http://www.cfm.va.gov/til/aeDesSubReq.asp (Click Vol. C Minor and NRM Projects).
Comply with VA TIL, PG-18-12 Design Guides, https://www.cfm.va.gov/til/dGuide.asp

Any deviation from requirements, standards and guidelines (to any extent) shall be fully presented by the A/E and fully discussed with the design team. The A/E is responsible for documenting the issue, discussions and resolutions, including detailed reasons, contributing factors and justification for deviation. The A/E shall attribute a deviation to VA input or direction. The A/E shall retain all responsibility for a compliant design and shall stamp the design, certifying compliance without any exceptions.
New rooms and partitions shall be designed tight to reduce sound and air transfer. The target sound transmission class is 40 STC. This includes in-wall components such as doors, frames, boxes and glazing.
Comply with TVHS Energy Requirements and Design Guide (revision September 2014, attached). See ASHRAE 90.1-2010 for energy requirements.
Ensure proper compliance with requirements, codes, guidelines, standards, etc.
Code Analysis will be clearly defined on a tracking sheet, with QA review and corrections prior to DD1. There shall be a stamped Life Safety sheet(s) as part of the CD1 package and final construction bid documents.
The A/E shall implement cost control measures / processes / reviews during every phase of planning and design.
Comply with current federal codes and guidelines, as well as applicable state and local codes. Comply with requirements, standards, codes and guidelines from other recognized authoritative bodies, such as The Joint Commission, American Society of Hospital Engineers, AIA & IBC. Other recognized bodies include but are not limited to; Associated Air Balance Council (AABC), American Concrete Institute (ACI), Acoustical and Insulating Materials Association (AIMA), American Society of Heating, Refrigeration, and Air-Conditioning Engineers (ASHRAE), American Society of Mechanical Engineers (ASME), American Society for Testing and Materials (ASTM), Gypsum Association (GA), International Building Code (IBC), National Electric Code (NEC), NFPA, National Environmental Balancing Bureau (NEBB), International Plumbing Code (IPC), OSHA, Sheet Metal and Air Conditioning Contractors National Association (SMACNA), and American Disabilities Act (ADA), American Barriers Act (ABA), Controlled Environment Testing Association (CETA) and United States Pharmacopeia (USP).
Design shall consider industry standards and best practices, as well as facility standards, incorporating them to arrive at optimal design solutions.

The A/E and the A/E s Commissioning Agent(s) shall comply with commissioning requirements in this SOW and with the commissioning requirements associated with any individual referenced regulations, codes, standards (such as AIA, ASHE, ASHRAE, etc.), including commissioning of architectural work. Commissioning shall focus on providing a complete, working product that complies with all codes/standards/guidelines for all trades. Also, perform all applicable commissioning work as indicated in the VA TIL Specifications Sections for commissioning requirements (General 01 91 00 Commissioning Requirements, 21 08 00 Commissioning of Fire Suppression System, 22 08 00 Commissioning of Plumbing Systems, 23 08 00 Commissioning of HVAC Systems, 26 08 00 Commissioning of Electrical Systems, 27 08 00 Commissioning of Communications Systems, 28 08 00 Commissioning of Electronic Safety and Security Systems, etc.).


V. DETAILED SUBMISSION REQUIREMENTS
Program Guide PG-18-15, establishes the guidelines for the A/E submissions. Design shall be performed and submitted in accordance with VA A/E Submission Instructions for Minor and NRM Construction Program. Refer to (http://www.cfm.va.gov/til/aeDesSubReq.asp). These guidelines indicate a level for submission compliance, which may not be adequate for certain, types of design. In some instances in which critical decisions need to be made, sufficient and relevant information has to be provided timely in order for the design to progress to meet certain milestone dates. The level of applicability of the program guide depends upon the scope of work and the exclusions, which are herein specified. Questions in regards to the applicability of specific requirements shall be resolved with the COR prior to any submission deadline. Where days are stated, this refers to calendar not work days (unless stated otherwise).
A. At each submission, all drawings and support material shall be dated and appropriately labeled above the title block:
Work Element
Copies
Duration
Notes
Delivery
Kick-off Meeting &
Initial Interview/Survey

1 Day


Initial Site Survey & Interviews

2 Days


Initial Survey/Interviews and Exit Interview Meeting

1 Day

Documented questions & answers/resolutions
Schematic Design (SD) and Assessment
4
21 Days
Plan on survey trips to site
Drawings of Existing Conditions for each trade/discipline
Follow-up Interviews and Surveys

1 Day

Documented questions & answers/resolutions
Conceptual and Schematic Submission Review Meeting
4
1 Day

Electronic copies & hardcopy (2 Full Size & 2 Half Size + 1 spec)
Gov t Review

7 Days


Conceptual and Schematic Submission Review Conference Call

1 Day
Approvals (signatures by key design team personnel and User)

Design Development 1 (DD1)

28 Days


DD1 Submission Review Meeting
4
1 Day
Approvals (signatures by key design team personnel)
Electronic copies & hardcopy (2 Full Size & 2 Half Size + 1 spec)
Gov t Review

7 Days


Design Development 2 (DD2)

21 Days


DD2 Submission Review Meeting
4
1 Day

Electronic copies & hardcopy (3 Full Size & 1 Half Size including set for VA Energy Review +1 spec)
Gov t Review

7 Days


Construction Development 1 (CD1)

21 Days


CD1 Submission Review Meeting
4
1 Day

Electronic copies & hardcopy (3 Full Size & 1 Half Size including stamped set for VA 3rd party Life Safety review +1 spec)
Gov t Review

7 Days


Construction Development 2 (CD2)

14 Days


CD2 Submission Review Meeting
4
1 Day
Approvals (signatures by key design team personnel)
Electronic copies & hardcopy (2 Full Size & 2 Half Size + 1 spec)
Gov t Review

7 Days


Final Revision and Reproduction of Bid Documents

7 Days


Final VA Check
4
1 Day

Electronic copies & hardcopy (2 Full Size & 2 Half Size + 1 spec)
Total

159 Days



VA submission review comments may be verbal, noted directly on review sets, or written list. The A/E shall be responsible for compiling and addressing review comments. A/E shall produce and distribute meeting notes or minutes for VA review immediately after each submission review meeting. A/E shall track all design team comments/issues and the resolutions on an Excel tracking sheet with dates and points of coordination / contact.

In addition to the deliverables identified in Section A of Detailed Submission Requirements above and in the Requirements for A/E Design SubmissionsB in the VA Technical Information Library http://www.cfm.va.gov/til/aeDesSubReq.asp, A/E shall provide the following:
Separate Life Safety sheet(s). A/E shall furnish with drawings separate stamped Life Safety sheet(s). CD1 Life Safety drawings will be stamped and ready for VA 3rd party review. The final drawing/submission set will reflect all comments and/or revisions in accordance with VA provided 3rd party life safety review.
QA team red-line mark-ups. Corrections shall be made prior to submission to VA. Red-line mark-ups shall be submitted to the VA with each, corrected submission.
A/E submission checklists filled out by the A/E and submitted with each submission (see Program Design Guide, PG-18-15, Vol. C, latest revision)
With each submission, provide QA Commissioning Agent tracking sheet, documenting issues through discussions, implementation, resolution and corrections to ensure a clear path to code compliance.
D. For each submission, furnish electronic files in the latest version of Microsoft Office and Microsoft Word and/or AutoCAD 2016, as well as PDFs. Submit 4 hardcopies of all drawings (see additional delivery notes in table above) and 1 hardcopy set of specifications. This includes a full size hard copy at DD2 for energy review/comments. This also includes a full size hard copy of CD1 submittal with Life Safety sheets stamped for VA contracted 3rd party Life Safety review/comments.
E. The final construction bid documents will also include 2 full sets and 2 half sets plus 1 set of specifications, including all disciplines/packages and will be stamped (sealed and signed by the Architects and Engineers of Record).
F. Incomplete submissions will not be accepted or reviewed. Partial submissions or piecemealed information is considered to be incomplete and will not be accepted. Submissions and final construction bid documents shall incorporate or address all VA supplied comments from the previous submission package review(s) or it will be considered to be incomplete. Submissions packages shall undergo QA review and designer corrections prior to each submission. Submissions that have not been corrected shall not be accepted. Submissions without the required designer redline mark-ups and up-to-date QA tracking sheet will not be accepted.
G. If the submission documents are not complete, the A/E must resubmit the package in its entirety.
Total time to accomplish Schematics through final reproduced construction bid documents shall be 159 calendar days from the issuance of the Notice to Proceed. Each submission will require maximum 7 calendar days for VA review the consultant s submission package. A/E shall prepare a submission schedule based upon the submission table above so that the timeframes are met.
VI. CONSTRUCTION PERIOD SERVICE REQUIREMENTS
Review of Submittals: A/E and A/E s Commissioning Agent shall review all material submittals, shop drawings, test reports, etc. Reviews shall be completed and submittals returned to the VA Project Engineer within 7 calendar days of the A/E's receipt of the submittal.
Review Analysis of Requests for Information, Change Orders, and Costs: A/E shall provide prompt response when contacted by the Contracting Officer, or COR, to review and provide analysis of construction contractor requests for information; change orders; and resulting cost adjustments due to omissions, errors, ambiguities, etc. RFI response time shall be 5 calendar days.
Mandatory Site Visits: The A/E shall have a full team (with all trades represented) attend the in-wall inspection, above ceiling inspection, equipment start-ups (2) and final inspection. The A/E must also participate in two Pre-Bid conferences (2), but a full team is not required. The Commissioning Agent s on-site activities shall be involved and driven by the requirements of their certification/report. However, at a minimum, the Commissioning Agent shall attend final inspection, TAB, controls/VFD testing, operational testing prior to final inspection, dynamic real-world operational testing, CETA testing/certification, and additional site visits (2 minimum) during construction visits.

Additional Site Visits: A/E shall provide 48 site visits (1 person for 3 hours) during the construction period, in addition to the Mandatory Site Visits listed above. A site visit unit is defined as a visit to the site by one individual for any part of a day when requested by the Contracting Officer. On this job, a site visit should last 3 hours and may require the use of multiple units when more than one individual or an extended period of time is needed to inspect an area of work. Only registered architects, engineers and/or the commissioning agent that are familiar with the project may make these site visits. The Contracting Officer Representative has the prerogative to determine the professional discipline(s) required for each site visit. The A/E shall notify the COR of their presence on site, before any work is performed, to document the number of individuals who are making the site visit. The A/E shall observe the construction, advise the COR of any deviations or deficiencies, and recommend appropriate corrective actions.
The A/E, when requested, shall assist the Contracting Officer and COR to interpret the construction documents and shall: (1) recommend any action(s) deemed suitable for the satisfactory prosecution of the construction work; (2) prepare any supplemental drawings, specifications or other documents that may be required to clarify or supplement the construction documents; and (3) assess the preparation of Construction Contract Modifications initiated by or through VA to be executed in accordance with the Construction Documents.
"Record Drawings" Requirement: A/E shall revise the solicitation documents if necessary and provide a complete set of all drawings showing actual, completed construction and reflecting any changes incorporated in the work on hard (bond) copy and on electronic media. Electronic media drawings shall be in AutoCAD 2016 and always electronically stamped. A/E shall load and demonstrate full AutoCAD compatibility at VA site. Compatibility means that data can be accessed directly by target system without translation or processing of data files. Problems shall be corrected to satisfaction of VA. Final electronic media specifications shall be in Microsoft Word 2016 and Adobe PDF.
Commissioning Report Requirement: Commissioning report (indicating full compliance with all applicable codes/standards/guidelines) shall include (but is not limited too) an overview/main narrative, a narrative for each discipline/trade, subcontractor certification letters of compliance, mechanical controls operational testing (72 hour minimum, repeated until passed/compliant), mechanical testing, test, adjust and balance (TAB) report, final inspection (with designers, COR, commission agent, contractor and subcontractors), training reports, statement and certification of compliance of all applicable codes, tests of multiple cycles and conditions, lists of issues with actions taken and resolution/correction dates, operational tests with observation report of the final, real-world, working system / environment and CETA inspection report indicating full compliance with USP 797 and 800.
VII. MATERIALS TO BE FURNISHED TO THE SELECTED A/E BY VA

Drawing files will be made available. AutoCAD drawing files are available only for architectural floor plans. Utility drawing files are incomplete and only available as hard copies, but can be made available for the A/E to copy and scan. The accuracy of drawings is not guaranteed and shall be used for general information only. Actual conditions shall be fully surveyed in the field by the A/E, then drafted and reverified by the A/E.
Existing Architectural Floor Plan of Murfreesboro VAMC, Building 3. (PDF and AutoCAD)
Cut Sheets of VA equipment

The recent Pharmacy Test Reports

Additional TVHS Energy Conservation Project Requirements and Design Guide

VIII. CONSULTANT AND DESIGNER QUALIFICATIONS
The consultant shall provide a team of professional designers and engineers that have worked together before on USP 797 and USP 800 projects that are capable of completing the work as specified. The consultant shall not make changes in personnel from those who are approved on the team without prior approval from the VA Contracting Officer and the Contracting Officer s Representative (COR). Approval of changes will not be granted without overwhelming reason, such as death, termination or severe health issues. Personnel changes solely benefiting the consultant will not be approved. Replacement personnel must be approved by the VA and must have equal or greater qualifications to the departed team member.
The Team must have, for a USP 797 regulated space:
Worked together a minimum of 5 years;
10 completed projects within last 5 years in design or construction;
15 completed testing or certification projects.
The Team must have, for a USP 800 regulated space:
Worked together a minimum of 2 years;
3 ongoing or completed projects within the last 2 years in design or construction
10 ongoing or completed testing or certification projects.
Firm will produce training certificates for the principle engineer, lead architect, lead mechanical engineer and commissioning agent that show 90 hours of continuing education on USP 797 compliance within last 3 years.
Firm will produce training certificates for the principle engineer, lead architect, lead mechanical engineer and commissioning agent that show 60 hours of continuing education on USP 800 compliance within last 3 years.
Designers on the team must have the following:
Licensed in United States and able to stamp designs / drawings.
Experience with one similar USP 800 design; Experience with 5 similar USP 797 designs; Team members shall provide a list of USP 800 and USP 797 projects that they have stamped within the last 5 years.
At least, one CETA member that has been certified within the past 2 years.
Similar projects have a construction dollar amount over $500,000
Deliverables for submitted personnel shall be:
Referenced similar projects shall include, at a minimum, facility name, location, project title and total project budget.
A facility engineering and pharmacist supervisor as point of contact for each project with name, email, and phone number.
IX. GEOGRAPHICAL LOCALITY
The A/E shall be geographically located within the continental United States. A/E must be capable of scheduling and arriving at the Murfreesboro Campus within 5 days if needed.

The design of architectural, structural, mechanical, electrical, civil or other engineering features of the work shall be accomplished by registered or certified architects or engineers within the Continental United States.

The AE shall, when requested, without additional expense to the Government be responsible for obtaining any necessary licenses and permits in connection with performance of this contract of any possible construction based on the results thereof (including but not limited to reports, plans, specifications, location, time, estimated cost of construction or estimated Value Engineering savings) or except to authorized Government personnel or upon prior written approval of the Contracting Officer.
AE firms submitting SF330 s for review under this project will be evaluated based on the following selection criteria:
Professional qualifications necessary for satisfactory performance of required services;

Specialized experience and technical competence in the type of work required, including, where appropriate, experience in energy conservation, pollution prevention, waste reduction, and the use of recovered materials;

Capacity to accomplish the work in the required time;

Past performance on contracts with Government agencies and private industry in terms of cost control, quality of work, and compliance with performance schedules;

Location in the general geographical area of the project and knowledge of the locality of the project; provided, that application of this criterion leaves an appropriate number of qualified firms, given the nature and size of the project;

Reputation and standing of the firm and its principal officials with respect to professional performance, general management, and cooperativeness;

Record of significant claims against the firm because of improper or incomplete architectural and engineering services; and

Specific experience and qualifications of personnel proposed for assignment to the project and their record of working together as a team.

4 hour on-site response time

Acceptability under other appropriate evaluation criteria.
NAICS code 541330 is applicable to this requirement. The small business size standard is $15M.
VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (DEC 2009)
(a) Definition.B For the Department of Veterans Affairs, Service-disabled veteran-owned small business concern :
(1) Means a small business concern:
(i) Not less than 51 percent of which is owned by one or more service-disabled veterans or, in the case of any publicly owned business, not less than 51 percent of the stock of which is owned by one or more service-disabled veterans (or eligible surviving spouses);
(ii) The management and daily business operations of which are controlled by one or more service-disabled veterans (or eligible surviving spouses) or, in the case of a service-disabled veteran with permanent and severe disability, the spouse or permanent caregiver of such veteran;
(iii) The business meets Federal small business size standards for the applicable North American Industry Classification System (NAICS) code identified in the solicitation document; and
(iv) The business has been verified for ownership and control and is so listed in the Vendor Information Pages database, (http://www.VetBiz.gov).
(2) Service-disabled veteran means a veteran, as defined in 38 U.S.C. 101(2), with a disability that is service-connected, as defined in 38 U.S.C. 101(16).
(b) General.B (1) Offers are solicited only from service-disabled veteran-owned small business concerns. Offers received from concerns that are not service-disabled veteran-owned small business concerns shall not be considered.
(2) Any award resulting from this solicitation shall be made to a service-disabled veteran-owned small business concern.
(c) Agreement.B A service-disabled veteran owned small business concern agrees that in the performance of the contract, in the case of a contract for:
(1) Services (except construction), at least 50 percent of the cost of personnel for contract performance will be spent for employees of the concern or employees of other eligible service-disabled veteran-owned small business concerns;
(2) Supplies (other than acquisition from a non-manufacturer of the supplies), at least 50 percent of the cost of manufacturing, excluding the cost of materials, will be performed by the concern or other eligible service-disabled veteran-owned small business concerns;
(3) General construction, at least 15 percent of the cost of the contract performance incurred for personnel will be spent on the concern s employees or the employees of other eligible service-disabled veteran-owned small business concerns; or
(4) Construction by special trade contractors, at least 25 percent of the cost of the contract performance incurred for personnel will be spent on the concern s employees or the employees of other eligible service-disabled veteran-owned small business concerns.
(d) A joint venture may be considered a service-disabled veteran owned small business concern if
(1) At least one member of the joint venture is a service-disabled veteran-owned small business concern, and makes the following representations:B That it is a service-disabled veteran-owned small business concern, and that it is a small business concern under the North American Industry Classification Systems (NAICS) code assigned to the procurement;
(2) Each other concern is small under the size standard corresponding to the NAICS code assigned to the procurement; and
(3) The joint venture meets the requirements of paragraph 7 of the explanation of Affiliates in 19.101 of the Federal Acquisition Regulation.
(4) The joint venture meets the requirements of 13 CFR 125.15(b).
(e) Any service-disabled veteran-owned small business concern (non-manufacturer) must meet the requirements in 19.102(f) of the Federal Acquisition Regulation to receive a benefit under this program.
Project 626-15-201, Replace Handling Unit 2, will be procured in accordance with The Brooks Act of 1972, Federal Acquisition Regulation (FAR) 36.6 and VA Acquisition Regulation 836.6.
THIS ANNOUNCEMENT IS NOT A REQUEST FOR PROPOSAL. NO SOLICITATION PACKAGE WILL BE ISSUED UNTIL AFTER AN EVALUATION HAS BEEN MADE ON THE PROVIDED SF-330s.
Acceptable Electronic FormatsB (Software) for Submission of Offers
Files readable using the current Microsoft* Office version Products: Word, Excel, and PowerPoint.B Please see security note below for caution regarding use of macros. When submitting construction drawings contractors are required to submit one set in AutoCAD and one set in Adobe PDF. (purpose: contracting can open the PDF version and engineering can open AutoCAD files);

Files in Adobe* PDF (Portable Document Format) Files:B When scanning documents scanner resolution should be set to 200 dots per inch, or greater;

Other electronic format. If you wish to submit an offer using another format other than described in these instructions, e-mail the Contracting Officer who issued the solicitation. Please submit your request at least ten (10) calendar days before the scheduled closing date of the solicitation.B Request a decision as to the format acceptability and make sure you receive approval of the alternate format before using it to send your offer; and

Please note that we can no longer accept .zip files due to increasing security concerns.

E-mail Submission Procedures: For simplicity in this guidance, all submissions in response to a solicitation will be referred to as offers.
Subject Line: Include the solicitation number, name of company, and closing date of solicitation;

Size: Maximum size of the e-mail message shall not exceed five (5) megabytes. Only one email is permitted unless otherwise stated in this paragraph or in writing by a Contracting Officer; and

The offer will be date and time stamped by the Microsoft Email system and will be the official record of receipt for the submission.

E-mail questions to: jason.kinchen@va.gov Submissions must be received No Later Than 2:00 PM ET on August 16, 2018. Submission by Electronic Mail is AUTHORIZED. Submitted SF330 s are not to exceed a total of fifty (50) pages INCLUDING cover page and any other submitted documents

Send 330s to: Jason Kinchen
615-225-6506
Jason.kinchen@va.gov

This is not a Request for Proposal. This Notice is seeking information only from qualified Architectural and Engineering firms with the capability to perform the work. The government will not provide any reimbursements to contractors submitting their qualification for this requirement.

Jason K. Kinchen
jason.kinchen@va.gov

jason.kinchen@va.gov

    1. Home
    2. Articles
    3. Login or Register

    4. Search

    5. Add/Announce your RFP