The RFP Database
New business relationships start here

A/E Design Project No. 667-18-119 Upgrade Water Distribution System, Main Hospital for the Overton Brooks VA Medical Center, Shreveport, LA


Mississippi, United States
Government : Federal
RFP
Go to the link
This document has expired, therefore the above link may no longer work.

CONTRACT INFORMATION: General. A-E Services are being procured in accordance with the Selection of Architects and Engineers Statute (Public Law 92-582), formerly known as the Brooks Act, and implemented in Federal Acquisition Regulation (FAR) 36.6. All submissions will be evaluated in accordance with the evaluation criteria. The Government will not pay, nor reimburse, any costs associated with responding to this
request. The Government is under no obligation to award a contract as a result of this announcement. Firms will be selected based on demonstrated competence and qualifications for the required work. The NAICS Code for this acquisition is 541330 Engineering Services and the applicable Small Business Size Standard is $15.0M. The area of consideration is RESTRICTED to a 500 mile radius of the Overton Brooks VA Medical Center, 510 E. Stoner Avenue, Shreveport, LA 71101-4295 in which either the A/E firm s Primary or established Auxiliary/Satellite office must be located. Note: The 500 mile radius will be measured by one or more of the nationally recognized commercial free on-line mapping services from the Primary or established Auxiliary/Satellite Office Address to the above VA address (shortest driving distance option).

Contract Award Procedure: The proposed A/E services will be obtained by a Negotiated Firm-Fixed Price Contract. Interested parties shall ensure current Licensing and have a current registration in the System for Award Management (SAM) database at https://www.sam.gov and the Vendor Information Pages database at http://www.va.gov/osdbu well as have submitted the current cycle VETS-4212 Report http://www.dol.gov/vets/programs/fcp/main.htm (for contracts in the amount of $150,000.00 or more) Failure of a proposed SDVOSB to be certified by the CVE at the time the SF 330 is submitted shall result in elimination from consideration as a proposed contractor.

SDVOSB Requirements: In accordance with VA Notice of Total Service-Disabled Veteran-Owned Small Business Set-Aside, a service disabled veteran-owned small business concern agrees that, in the performance of the contract, at least 50 percent of the cost of personnel for contract performance will be spent for employees of the concern or employees of other service-disabled veteran-owned small business concerns.

c. Design Costs: All offerors are advised that in accordance with VAAR 836.606-73(a) the total cost of the architect or engineer services contracted for must not exceed 6 percent of the estimated cost of the construction project plus any fees for related services and activities. Additionally, FAR 52.236-22 Design Within Funding Limitations, will be applicable to this procurement action. Design limitation costs
will be provided to the most highly rated AE firm selected to complete the design. The magnitude for construction (not design) of this project is between $1,000,000 and $2,000,000.

SELECTION CRITERIA: The selection criteria for this acquisition will be in accordance with FAR 36.602-1 and VAAR 836.602-1 and are listed below in descending order of importance. The completed SF 330 will be evaluated by the Overton Brooks VA Medical Center Evaluation Board in accordance with FAR 36.602-5(a) Short Selection Process for Contracts Not to Exceed the Simplified Acquisition Threshold and the selection report shall serve as the final selection list which will be provided directly to the Contracting Officer.
(1) Professional qualifications necessary for satisfactory performance of required services;
(2) Specialized experience and technical competence in the type of work required;
(3) Capacity to accomplish the work in the required time;
(4) Past performance on contracts with Government agencies and private industry in terms of cost control, quality of work, and compliance with performance schedules;
(5) Location in the general geographical area of the project and knowledge of the locality of the project (500 miles);
(6) Reputation and standing of the firm and its principal officials with respect to professional performance, general management, and cooperativeness.
(7) Record of significant claims against the firm because of improper or incomplete architectural and engineering services.
(8) Specific experience and qualifications of personnel proposed for assignment to the project and their record of working together as a team.
SUBMITTAL REQUIREMENT: This project is a 100% set-aside for Service-Disabled Veteran Owned Small Business (SDVOSB) concerns under VAAR 852.219-10, VA Notice of Total Service-Disabled Veteran-Owned Small Business Set-Aside (Dec 2009). All original Standard Form (SF) 330 packages shall be submitted to:

Gulf Coast Veterans Health Care System
Network Contracting Office 16 (NCO 16)
ATTN: Cynthia L. Kinsman Bldg T102 Rm A110
400 Veterans Ave
Biloxi, MS 39531

(a) All SF 330 submissions shall be clearly marked with the subject line displaying the Solicitation Number 36C25618R0181. The SF 330 form may be downloaded from
http://www.gsa.gov/portal/forms/type/SF. Completed SF 330 s shall include the primary firms, subcontractor firms, and any consultants expected to be used on the project.

(b) Firms that meet the requirements listed in this announcement are invited to submit three (3) copies of the completed SF 330 including Parts I and II as described herein, to the above address no later than 3:30 P.M. (CST) on THURSDAY - JANUARY 25, 2018. FAX AND/OR E-MAIL SUBMISSIONS WILL NOT BE ACCEPTED. Late proposal rules found in FAR 15.208 will be followed for late submittals.

(c) Interested firms shall address each of the Eight (8) Selection Criteria in their SF 330 s and additional documents/submittals.

THIS IS NOT A REQUEST FOR PROPOSAL. THERE ARE NO SOLICITATION DOCUMENTS AVAILABLE. This is a request for SF 330 s Architect/Engineer Qualifications packages only. Any requests for a solicitation will not receive a response. This requirement is subject to Availability of Funds.

PROJECT INFORMATION:
Request for Proposal to Design
Project No. 667-18-119
Upgrade Water Distribution System, Main Hospital
Overton Brooks VA Medical Center
510 E. Stoner Avenue
Shreveport, LA 71101

General Information

A 1.0 Project Background, Description and Scope of Work

Provide Architect/Engineer professional services to include design development, construction documents, specifications, cost estimates, construction period services and construction site visits.

Overton Brooks VAMC (OBVAMC) seeks Architectural and Engineering (AE) design services to evaluate and improve the existing domestic water distribution system [Hot Water (HW) and Cold Water (CW)] for the Main Hospital, Water Storage Tanks and Cooling Towers to prevent Healthcare-Associated Legionnaire s Disease (HCA-LD) and comply with the VHA Water Safety Program as described in the VHA Directive 1061

This contracted work includes preparation of drawings, specifications and cost estimates for all facets of work and trades necessary to facilitate award of a construction contract to address domestic water quality and Legionella prevention initiative throughout the main hospital. This project will install a secondary water treatment system. Additionally, this project will study and address dead legs, scald guard protection, water flushing, water testing and water monitoring measures throughout the main hospital. The work involved will need to include infection control measures and as this is occupied space, planning for phasing the construction work is required.

The AE design team shall:

Perform site investigations necessary to design a secondary water treatment system(s) for enhanced control of the Chlorine and biocide levels throughout the main hospital, water storage tanks and cooling towers (all HW and CW systems).
Perform site investigations necessary to assess the existing chlorine/biocide monitoring equipment and identify and modifications required to adequately monitor levels within the main hospital (all HW and CW systems).
Perform site investigations with the intent to identify dead-ends for removal and any asbestos abatement required to perform the work (all HW and CW systems).
Perform site investigations with the intent to consider adding scald guard protections devices where needed (HW system).
Perform site investigations with the intent to consider automatic cycling faucets on distal fixtures served by extended domestic water piping runs (all HW and CW systems).
Perform site investigations necessary to develop single-line drawings (all HW and CW systems) and a Revit model of the existing domestic water piping distribution system of the main hospital, water storage tanks and cooling towers and identify modifications required (preferably accessible) to the existing system to comply with the VHA Water Safety Program as described in the VHA Directive 1061.
NOTE: Please report any leaks found during the survey of the existing water distribution system immediately to the COR for repair by OBVAMC Maintenance Staff

The deliverables for this project include, but not limited to, the design and construction document preparation of the following to comply with the VHA Water Safety Program as described in the VHA Directive 1061:

Secondary water treatment and continuous monitoring system(s).
Identification and removal of piping dead-ends.
Identification and abatement of any asbestos containing material.
Identification and installation of any required scald guard devices.
Identification and installation of needed automatic cycling faucets on distal fixtures served by extended domestic water piping runs.
Development of a testing, flushing and preventative maintenance program to maintain the water distribution system for the main hospital at the appropriate levels to mitigate the development of Legionella.
Accurate representations of the existing and post-construction water distribution system for the main hospital, water storage tanks and cooling towers (all HW and CW systems) in a schematic (single line) diagram.

The design shall also incorporate proper construction phasing of work with time limitations. Access and continued function/operation of adjacent occupied spaces (above, below and beside) shall be considered within the construction phasing plan to minimize the overall impact and disruptions generated by the construction activities.

This contract will provide for complete site investigation, design (construction documents), construction period services (CPS) and construction site visits.

PERIOD OF PERFORMANCE

The delivery date for this contract shall be 200 days from Notice to Proceed.

LOCATION

Overton Brooks Veterans Affairs Medical Center
510 E. Stoner Ave.
Shreveport, LA 71101

TERMS OF THE SOLICITATION

The term responsibility, used in the instructions that follow, includes architectural and engineering design, cost, schedule and construction responsibility for completion of this project in accordance with the documents of this RFP for OBVAMC project no. 667-18-105. It is the responsibility of the Design Offeror or A/E to provide complete Design Documents (drawings and specifications) for a fully functional facility. Omissions in this RFP and Technical Requirements do not relieve the Design Offeror from providing a complete and fully functioning design package and service.
The terms Design Team , Design Offeror , AE or A/E refers to the successful design team. The design team shall consist of a Service Connected (Disabled) Veteran Owned Small Business architectural/engineering firm and all associated consultants and subcontractors.
The term Design Team or engineer refers to registered/licensed Architects and Engineering professionals.
The terms the work and project refers to the all site investigation, site survey, calculations, testing and design for documents to Upgrade the Domestic Water System, OBVAMC.
The term VA and the term VAMC refers to the Overton Brooks Veterans Affairs Medical Center in Shreveport, LA.
The VAMC Coordinator and COR (Contracting Officer s Representative) for this project is Stacy Walden at 318-990-5277, stacy.walden@va.gov
The CO (Contracting Officer) for this project is to be determined (TBD).

QUALITY ASSURANCE/QUALITY CONTROL (QA/QC)

The Design Offeror or A/E shall develop, execute and demonstrate that the project plans and specifications have gone through a rigorous review and coordination effort. The A/E shall provide an outline of the actions that the firm will take during the design process to ensure a quality finished design is achieved.

COST ESTIMATE

A detailed estimate of construction cost (using RS Means, Cost Works) and Market Study/Survey shall be provided with each design submission.

DRAWINGS

This project will utilize AutoCad, version 2015. All VA design guides and requirements can be found online at: http://www.cfm.va.gov/TIL/. Where conflicts occur between VA standards and applicable codes, the most stringent requirement shall govern. All drawings must be bundled using the e-transmit function.

SITE AND TOPOGRAPHY SURVEY

During the design phase, the A/E will coordinate with VAMC Staff to perform a site survey to facilitate the design. A topographic survey is NOT required.

GEOTECHNICAL SURVEY

A geotechnical survey of the area is NOT required.

UTILITY SURVEY

During the design phase, the A/E will coordinate with OBVAMC Staff to obtain utility information to facilitate the design. Otherwise, what is not obtained shall be surveyed to extent necessary by the A/E. A/E shall procure any services (to include, but not limited to HVAC air and hydronic pre-testing and evaluation) required to adequately test and determine the capacity of the existing utility system.

ASBESTOS ABATEMENT SURVEY

During the design phase, the A/E will coordinate with VAMC Staff to perform an asbestos abatement survey to facilitate the design. The AE shall survey the areas of conflict in question to incorporate into the design documents accordingly.

FIRE PROTECTION ENGINEER REVIEW & CERTIFICATION

The A/E shall have the design plans and specifications reviewed by a registered Fire Protection Engineer (FPE) to ensure the design proceeds in accordance with Life Safety Code (LSC) and applicable National Fire Protection Association (NFPA) codes. The FPE s review comments shall be provided along with each design submittal starting with the 50% Design Development drawings. With the Final 100% Construction Documents submittal, provide a FINAL certification letter from a registered FPE stating that the FINAL plans and specifications are in compliance with the current LSC and NFPA codes.

SEISMIC DESIGN

In accordance with the VA s manual for Seismic Design Requirements (H-18-8), OBVAMC Shreveport, LA seismicity is identified as being Low (per Table 4: Spectral Response Accelerations at VA Facilities, pg. 23); therefore, seismic design is NOT required.

PHYSICAL SECURITY & BLAST DESIGN

The design shall be in accordance with the latest edition of the Physical Security Design Manual for VA Facilities, Life-Safety Protected/Mission Critical Facilities as applicable. NOT required for this design effort.

HANDICAP ACCESSIBILITY

The design will be required to comply with the Uniform Federal Accessibility Standards (UFAS), ABAAS (Architectural Barriers Act Accessibility Standards) and PG-18-13 (Barrier Free Design Guide) in all areas. NOT required for this design effort.

COMMISSIONING

The construction and intended use does require commissioning. The A/E shall incorporate the VA s commissioning specification into the design and complete set of construction documents as applicable. The Construction contractor shall procure the 3rd party Commissioning Agent to oversee and execute the contract required commissioning activities during Construction.

GOVERNMENT FURNISHED INFORMATION

The following is a list of government furnished information found on the VA s Technical Information Library website (http://www.cfm.va.gov/TIL/) to be used for this project, as applicable:
PG-18-1 Master Construction Specifications
PG-18-3 Design and Construction Procedures
PG-18-4 Standard Details and CAD Standards
PG-18-10 Design Manuals (by discipline)
PG-18-12 Design Guides (graphical, by function)
PG-18-13 Barrier Free Design Guides
Uniform Federal Accessibility Standards (UFAS)
ABAAS (Architectural Barriers Act Accessibility Standards)
Physical Security Design Manual for VA Facilities, Life-Safety Protected
NOTE: Utilize the latest version of guidance at time of design award.

A 2.0 Design Deliverables

OBVAMC Design Submissions Statement of Task:
Submit Floor Plan/Schematic Design
35% Design Development (DD)
65% Design Development (DD)
95% Design Development (DD)
100% Construction Documents (CD)


NOTE 1: Additional detailed design submission requirements can be found in VA Guide PG-18-15.
NOTE 2: The VA staff shall have a minimum timeframe (calendar days) as outlined in the design schedule, to review and coordinate each AE design submissions. If the VA workload does not allow for a thorough review within the designated timeframe, the AE shall not proceed to the next design phase until comments have been received from the VA. The AE will be entitled to a time only contract extension for the number of VA review days beyond the designated timeframe.

Schematic Design: Investigate and survey project site. Verify any VA provided data. AE is responsible for collecting all data required for the design. The A/E is responsible for measuring and collecting actual field data that may be required. The A/E shall evaluate the existing water distribution for the main hospital and make recommendations on what modifications to the existing system are required to comply with the VHA Water Safety Program as described in the VHA Directive 1061. A/E shall provide recommendation and associated construction cost. This schematic design phase is an iterative process and requires close coordination with the VA staff. The preliminary schematic design/layout will most likely require tweaking until a final plan/layout is officially approved by the hospital. Dimensions, slopes, etc will need to be indicated on the drawings. AE shall work with the VA staff until acceptable Water System Upgrade plan has been developed and approved in writing by the VA. The AE final deliverables for this phase are (hard and electronic copies):
OBVAMC Approved Water System Upgrade Plan
Preliminary Cost Estimate (RS Means, Cost Works)
List of probable Specification Sections for this project
Asbestos Survey

35% Design Development: These drawings shall be at the largest scale possible.

Drawings & Specifications: Provide one 22 x34 size set, five 17 x22 size sets, two 11 x17 size sets and one unbound 11 x17 size set of preliminary construction drawings. Provide one set of preliminary specifications indicating all the AE proposed edits double-sided and in a 3-hole punch binder. Drawings and specifications to indicate potential deductive bid alternates and any phasing requirements. Also, provide electronic copies on a CD (Drawings PDF format, Specifications in Word format).
Cost Estimate & Design Analysis: Provide a detailed cost estimate indicating labor, material and equipment cost in RS Means CostWorks format. Estimate shall include Prime Contractors (SDVOSB) Overhead, Profit, Bond, and Labor Burden (typically 32%). Estimate shall indicate feasible deductive bid alternates to bring the construction cost within the allotted construction budget. The cost estimate and design analysis shall be submitted in hard copy (double-sided and in a 3-hole punch binder) and an electronic copy on a CD.
FPE Certification: Provide an initial review by the Fire Protection Engineer and indicate their comments.

65% Design Development: This submission of drawings, specifications and cost estimate shall be very close to complete. This review by the VA shall be to validate that 35% comments were incorporated into the project. The construction documents should be sufficiently developed to cover all work items to be addressed by the project. No major items missing from this submission. The VAMC review of these documents should result in very minor comments to allow for the next 95% submission. AE shall provide a list of questions by discipline on anything that s needed from the VA to continue and fully develop the next 95% design submission. Additionally, the AE shall provide minutes from the last design review meeting and shall provide responses to all VA comments noted or identified during the last review submission.

Drawings & Specifications: Submit in the same manner as the 35% DD submittal.
Cost Estimate & Design Analysis: Submit in the same manner as the 35% DD submittal, except provide two complete sets of specifications and design analysis.
FPE Certification: Provide review by the Fire Protection Engineer and indicate their comments.

95% Design Development: This submission of drawings, specifications and cost estimate shall be complete. This review by the VA shall be to validate that 65% comments were incorporated into the project. There shall be nothing missing from the construction documents. The VAMC review of these documents should result in very minor comments to allow for the next submission to be final. AE shall provide a list of questions (which should be very minimal at this point) by discipline on anything that s needed from the VA to finalize and completed the design documents. Additionally, the AE shall provide minutes from the last design review meeting and shall provide responses to all VA comments noted or identified during the last review submission. NOTE: If the VA s review of this set of documents (95%) results in numerous comments, then a 99% review or a check set of certain elements of the design will be required before the AE shall proceed to the 100% Final Construction Documents.

Drawings & Specifications: Submit in the same manner as the 65% DD submittal.
Cost Estimate & Design Analysis: Submit in the same manner as the 65% DD submittal.
FPE Certification: Provide review by the Fire Protection Engineer and indicate their comments.

100% Construction Documents: This submission shall incorporate all project requirements and previous comments. These documents shall be marked FINAL ready for bidding.

Drawings & Specifications: Submit in the same manner as the 65% DD submittal. ALL ENGINEERS AND ARCHITECTS PROFESSIONAL STAMPS SHALL BE ON THIS SET OF DOUMENTS.
Cost Estimate & Design Analysis: Submit in the same manner as the 65% DD submittal and marked FINAL.
FPE Certification: Provide a FINAL certification letter from a registered Fire Protection Engineer stating that the FINAL plans (annotate date on Final set of plan) and specifications are in compliance with the current Life Safety Code (LSC) and applicable National Fire Protection Association (NFPA) codes.
Electronic Copies: Provide two CD electronic copies of the entire package (Construction Drawings and Specifications). The drawings shall be as both AutoCAD (2015) binded and scanned individual PDF files (coordinate naming of the files with the COR). The specifications shall be in separate WORD format and separate PDF files for each spec section (coordinate naming of the files with the COR).

Construction Period Services (CPS): AE shall provide full post design services construction period service IAW the Special Provisions of this contract.

PRE-AWARD: CPS s to include assistance with questions, request for information (RFI s), meeting conference calls, clarifications and addendums during the construction solicitation phase.
POST-AWARD: CPS s also include full support through the construction phase to include but not limited to, assisting with questions, clarifications, inspections, reviewing and responding to RFI s and review/coordination of contract modifications/change orders. Designing and estimating of design omissions.
POST-AWARD SITE VISITS: CPS s shall also include a minimum of 8 Site Visits during the construction phase of the project. Type and discipline of site visit shall be determined at the time of need by the COR.
ASBUILTS: AE shall also incorporate contractor s asbuilt/redline drawings on AutoCAD (2015) binded, and provide both electronic (two CD s clearly labeled) and hard copy sets. Hard copy sets of asbuilt drawings shall consist of two 22 x34 size set, five 17 x22 size sets, two 11 x17 size sets and one full size set on mylars.

Cynthia Kinsman
Contracting Officer

Cynthia.Kinsman@va.gov

    1. Home
    2. Articles
    3. Login or Register

    4. Search

    5. Add/Announce your RFP